Fill quantities and fill height of BB902T
BB902T holds 0.89 m³ by calculation and carries 1,500 kg at safety factor 5:1. The table shows the weight of the full bag and the permitted fill height.
| Items | Material (guide value) | Bulk density t/m³ | Weight at full volume | max. fill height | Fill level |
|---|---|---|---|---|---|
| BB902T | Sand, dry | 1,50 | 1,335 kg | full height, 110 cm | 100 % |
| BB902T | Gravel, chippings | 1,60 | 1,425 kg | full height, 110 cm | 100 % |
| BB902T | Rubble, mixed | 1,40 | 1,245 kg | full height, 110 cm | 100 % |
| BB902T | Soil, excavated material | 1,60 | 1,425 kg | full height, 110 cm | 100 % |
| BB902T | Cement, loose | 1,20 | 1,070 kg | full height, 110 cm | 100 % |
Guide values as in the Fill Limit Calculator; the measured bulk density of your material is what counts. With sand, BB902T stays below the load capacity.
Quantity planning with BB902T
How many BB902T do you need for a given quantity of material? The table uses the nominal volume of 0.89 m³ and 375 pieces per pallet. With sand (1.50 t/m³), the load capacity of 1,500 kg limits the fill quantity per bag to 0.89 m³.
| Items | Material quantity | Bags at full volume | Pallets | Bags for sand at the load capacity limit | Pallets |
|---|---|---|---|---|---|
| BB902T | 10 m³ | 12 | 1 | 12 | 1 |
| BB902T | 25 m³ | 29 | 1 | 29 | 1 |
| BB902T | 50 m³ | 57 | 1 | 57 | 1 |
| BB902T | 100 m³ | 113 | 1 | 113 | 1 |
Worked example for 100 m³ of material
How many BB902T are needed depends on the density: with light material the volume of 0.89 m³ fills the bag; with heavy material the load capacity of 1,500 kg is reached earlier.
- Sand, dry (1.50 t/m³): 100 m³ weigh 150 t. One BB902T takes 0.89 m³ or 1,335 kg; the volume of 0.89 m³ sets the limit. You need 113 pieces, which is 1 pallets.
- Gravel, chippings (1.60 t/m³): 100 m³ weigh 160 t. One BB902T takes 0.89 m³ or 1,425 kg; the volume of 0.89 m³ sets the limit. You need 113 pieces, which is 1 pallets.
- Rubble, mixed (1.40 t/m³): 100 m³ weigh 140 t. One BB902T takes 0.89 m³ or 1,245 kg; the volume of 0.89 m³ sets the limit. You need 113 pieces, which is 1 pallets.
- Soil, excavated material (1.60 t/m³): 100 m³ weigh 160 t. One BB902T takes 0.89 m³ or 1,425 kg; the volume of 0.89 m³ sets the limit. You need 113 pieces, which is 1 pallets.
- Cement, loose (1.20 t/m³): 100 m³ weigh 120 t. One BB902T takes 0.89 m³ or 1,070 kg; the volume of 0.89 m³ sets the limit. You need 113 pieces, which is 1 pallets.
Handling of BB902T
- BB902T has four lifting loops. With BB902T, always attach all four; crane and forklift are possible.
- BB902T has no skirt and is open at the top. If you want to keep dust in, cover the filled bag.
- BB902T is uncoated. Store it dry and covered; the fabric absorbs moisture.
- When filled, BB902T weighs up to 1,500 kg. Lifting equipment, lifting accessories and ground must be rated for this.
- A pallet holds 375 pieces of BB902T (5 bundles of 75 pieces). Store unused bags in their original packaging.
Open details for BB902T
For BB902T the data sheet gives one value unclearly or not at all: the fabric weight in g/m². It says “on request” there. We confirm the value in writing before your order. Plan lifting equipment, filling and number of pallets only with it, and ask via the enquiry form.